Ky Power Proposes $2.85 Billion Natural Gas Plant in LC Being the First Major Plant in Decades; New Power Plant Could be Operating by 2031

By Roberta Cantrell
BSN Editor

Kentucky Power is requesting the states approval to build a natural gas power plant near Louisa to support an $8.5 billion data center development in northeastern Kentucky.

The proposed facility would be built at the existing Big Sandy power plant site generating approximately 760 megawatts of electricity at an estimated cost of $2.85 billion.

The proposal to build the ​power plant would be the first major power plant Kentucky Power has built in decades. Currently, Kentucky Power serves about 162,000 customers across 20 Eastern Kentucky counties and is a subsidiary of Ohio-based American Electric Power.

The project is part of TeraWulf’s planned Muskie Data Campus in Boyd and Greenup counties, which could require up to 1,000 megawatts of electricity by 2029.

Kentucky Power is also requesting approval for a new transmission substation in Boyd County and temporary electricity purchases from facilities in other states.

In a provided statement, Kentucky Power president and chief operating officer Cindy Wiseman said the utility’s commitment to Eastern Kentucky “goes beyond providing reliable electricity.”

“We’ve served these communities for generations, and we want our customers and communities to share directly in the benefits when new investment comes to the region,” Wiseman said. “Eastern Kentucky has a tremendous opportunity ahead, and thoughtful growth can strengthen our electric system, support good jobs and attract new investment.”

It was reported that in its application to the state’s utility regulator, the Kentucky Public Service Commission, Kentucky Power argues the combined cycle natural gas turbine, generating up to 769 megawatts of electricity, is needed to meet the demands of a hyperscale data center planned by the investor-owned company TeraWulf with an electricity demand of 1 gigawatt, or 1,000 megawatts. 

The electric utility wrote it had compared other options including a smaller gas-fired turbine and renewable energy but needed a “a more energy dense resource” for near-constant demand of the data center. The cost of building combined cycle turbines has surged this year because of electricity demand from data centers. The utility is seeking to buy fossil fuel-fired power from elsewhere until the new power plant is put into service in 2031. 

The utility is also asking the regulator to approve a contract to serve TeraWulf, having TeraWulf agree to pay approximately $100 million over 10 years to offset residential utility bills in the winter estimated to be about $26 a month for each ratepayer during the winter. 

The proposals are currently under review by the Kentucky Public Service Commission.

The new power plant is projected to begin operating in 2031, pending regulatory approval.

Andrew Mortimer